CONSTRUCTION
MANAGEMENT CONTRACT
Definition
- This is an agreement to perform the services and the work for a
percentage or a fixed fee with the qualified general contracting
organization serving as the construction professional and expert on the
Building Team with the owner and architect/engineer from the beginning
of design throughout the completion of construction. The contract can be
converted to a Guaranteed Maximum Price Contract when the plans are
sufficiently complete to define the scope of the work.
Selection
Method - The owner should make a careful objective review of the
qualifications of interested general contractors, giving due
consideration to their experience in working with architects and
engineers on work of similar character during design development and
make an award to the one best qualified with an acceptable fee.
Owner’s
Requirements
-
Staff involvement and ability to make prompt decisions after
weighing the Building Team's recommendations.
-
-
Selection of architect/engineer who is willing to operate as a team
member and be receptive to the construction manager's
recommendations.
-
-
A
job where flexibility to change is important, whose time allowance
precludes waiting for completed bid documents or a job not easily
marketable because of lack of definition of scope, or size.
Advantages
-
Creates a "team" with the owner, general
contractor/construction manager, and architect/engineer, before
plans are developed.
- General
contractor/construction manager is available to give his advise on
construction feasibility, cost, site selection, and scheduling.
-
-
Time and cost saving by starting construction before all plans are
complete.
-
-
Ability to competitively bid, including public work in a public
letting situation, all the trade contracts on the job, while at the
same time having a qualified general contractor on the team from the
inception of design through final completion and acceptance of the
project.
Cautions
-
Final cost not guaranteed (unless converted when plans are
sufficiently completed to a Guaranteed Maximum Price Contract).
-
-
Burden on owner in selection of a general contractor experienced in
scheduling, cost control, plan and specification review, etc., and
who has management experience to act as a team member and qualified
to direct the work of the individual trade contractors.
-
-
Under many public bidding statutes, a construction manager is
precluded from performing work with his own forces.
DESIGN
- BUILD CONTRACT
Definition-
Agreement with one single administrative entity, the prime contractor,
who provides the design and construction under one contract. The
construction portion of the work may be done under a Lump Sum, a Cost
Plus, or Guaranteed maximum Price contract.
Selection
Method - Contract may be negotiated or competitively bid. IF
competitively bid, it is extremely difficult to compare proposals so
that the owner may be assured that he is selecting that proposal which
will result in the lowest ultimate cost. The owner must produce program
requirements and preliminary plans and specifications with as much
definition as possible. He must then make a careful cost-benefit
analysis of the proposals submitted.
An
added feature in reviewing the qualifications under a Design - Build
contract, of course, is the review of the capabilities and experience of
the contractor to control the design function. In certain states the
general contractor may perform this function within his own
organization; in others he must work with a separate architect/engineer
consulting firm, unless he has a corporate professional license to
practice architecture and/or engineering.
Owner’s
Requirements
-
Staff proficiency in monitoring costs and auditing.
-
-
Where there is to be competition on a price basis, the owner must
have extremely strong staff capabilities to evaluate the proposals
and make a proper cost-benefit analysis.
-
-
Demonstrated
ability to program requirements.
Advantages
-
Owner’s program and engineering staff can work directly and
closely on a continuing basis with one contract entity, experienced
in both the design and construction process.
-
-
Construction may be started before plans are complete and the work
phased which may produce a time savings for the entire project.
Cautions
In
other forms of contracting with three contracting identities the owner,
contractor, an architect/engineer there is a certain check and balance
system which does not exist under the Design-Build method. For example,
form, convenience, cost of maintenance and aesthetics may be unduly
sacrificed to low initial first cost. Even with the "building
team" concept under the construction management type of contract
there still exists the three identities - while cooperating, they are in
a sense independent.
The
burden on the owner to select a qualified contractor/designer becomes
even heavier than in the other forms of contract. When the price is
guaranteed and particularly where the contract has been let on
competitive basis, the owner must accept a certain lack of flexibility
in obtaining desired features of the work and may have to accept certain
details of the final design, which he considers undesirable.
LUMP
SUM CONTRACT
Definition-
Agreement to perform the work for one fixed price, regardless of cost to
the contractor.
Selection
Method - Competitive bidding among general contractors for construction
of the entire project under a single contract is preferred. Bidding may
be from a pre-selected list of bidders, or from anyone who wishes to
bid. In public work and some private work the bidders must furnish proof
of financial capability such as a bond or certified check. When using a
pre-selected list on private work, the owner and his architect/engineer
should carefully and objectively weigh capabilities of the contractors
while assembling the list; after the list is determined, when the bids
are received, he should award the job to the lowest bidder.
Pre-selection is not possible on most public work.
Owner’s
Requirements
-
Completed
detailed plans and specification.
-
-
Adequate professional inspection and supervisory personnel,
experienced in construction, either in house or from architects and
engineers.
-
-
Staff
and consultant proficiency in planning, budgeting, construction
feasibility and marketing construction.
-
-
Marketable job.
Advantages
-
Economy of contractor effort with his own money at risk.
-
-
Objectivity of selection on private work.
-
-
Final price known (assuming no changes in plans and specifications.)
-
-
Less bookkeeping and auditing expense.
Cautions
-
Owner and contractor may have opposite financial interests.
-
-
The complicated procedures required to process changes and the
resulting cost to both parties.
-
-
Delay in start of construction until plans are 100% complete and
bids taken.
-
-
Reliance on consultants to provide practical construction advice,
budgets, and schedules, prior to receipt of bids.
CO MPARISON
CHART
The
Associated General Contractors (AGC) of NH Building Committee has
drafted the following guidelines for use by project owners when
selecting the most appropriate construction contract method.
The
complexities and decisions that must be made in order to have a
successful construction experience can be overwhelming.
This guide is intended to answer some of the questions concerning
the three basic types of construction procurement contracts.
We
have provided a side-by-side comparison of the three contract types
which includes descriptions and examples of project for which each is
most and least suited.
We
hope that these materials will provide you, as a project owner, with the
information you need to make an informed decision regarding your next
construction contract.